140 meters of torch pylons straight into the sky 8000 cement piles embedded in the ground nearly 200 builders race against time with a total investment of about tens of billions of Jinling Petrochemical high-end daily chemicals project is "Nanjing Jiangbei New District speed" to refresh the progress bar! 💪💪💪💪💪
On April 11, at the site of Jinling Petrochemical high-end daily chemicals (Jiangbei Phase I) project located in Nanjing Jiangbei New Material Science and Technology Park, machines roared, vehicles shuttled, and nearly 200 engineering and construction personnel worked feverishly in their respective workstations. "Since the project officially started in March this year, foundation pretreatment construction is being carried out, and at present, 10 sets of cement mixing piling machines are 'on fire', and more than 8,000 cement piles have been driven down, with a total length of nearly 60,000 meters." Dai Jin, the person in charge of the project site, said. Jinling Petrochemical high-end daily chemical products project with a total investment of about 10 billion yuan, divided into three phases of construction, after the completion of the project will create the first domestic from the petroleum raw materials to the end product of the daily chemical new material industry clusters, annual output value is expected to reach 23 billion yuan. Among them, the first phase of the project plans to invest a total of 4.011 billion yuan, covering an area of more than 600 acres.
Around the open field, there is a cement mixing pile machine standing at intervals, forming a big circle around the whole plant. After the pile machine started to the underground "digging", while driving piles while filling cement, each cement pile deep into the ground 7 meters, and non-stop mixing. Zhang Jinbiao, the person in charge of the site of Beijing Orient Nova Survey and Design Co., Ltd, the construction unit, introduced: "On March 17th, we drove the first cement mixing piles, and the workers worked overtime to complete the foundation pre-treatment construction in 4 months, and then entered the prefabricated piles construction stage. At present, the construction is progressing smoothly and is fully able to meet the requirements of the project schedule."
Unlike ordinary projects, chemical facilities require higher safety, so they need to ensure the stability and bearing capacity of the foundation. "During the construction process, we improve the strength of cement mixing piles by lengthening the time of cement mixing, so that the cement mixing amount reaches the design value." Zhang Jinbiao introduced, the general cement mixing pile construction only needs 20 minutes, here to mix for 30 minutes, is to ensure the quality of the project, in order to ensure the construction progress, next week will also add four sets of mixing pile machine.
In the northwest corner of the plant, the 140-meter-high torch pylons stand tall and eye-catching. "Torch is a chemical plant to deal with exhaust gas device, due to the height of the reason, the torch pylons to advance the construction, Jinling Petrochemical fast and furious organization of the construction, ahead of schedule to complete the task, for the construction of the latter part of the lay a good foundation." Dai Jin introduced that the project has completed the "four passes and one leveling", built 1900 meters of concrete roads and more than 2,000 meters of fences, the site of water, electricity and communications.
According to the project construction plan, the whole first phase of the project is planned to be mechanically completed in January 2027, and then transferred to the production preparation stage, and in May 2027, qualified products are to be produced. In order to accelerate the progress of the entire project, in addition to the construction of the plant, the procurement of production equipment is also being carried out simultaneously.
The process flow of chemical products is long and requires many production equipment in series, and most of this equipment needs to be customized, including long-cycle production equipment over 10 months, sub-long-cycle production equipment from 6 to 10 months, and general equipment under 6 months. "We are also currently in the midst of our equipment procurement process, with the purchase of two long-cycle production machines already in place, and the procurement of other equipment in progress." Dai Jin said.
It is understood that Jinling Petrochemical has the only alkylbenzene production unit in Sinopec and is the main production base for detergent raw materials in Asia. This project will give full play to the advantages of Jinling Petrochemical, extend the alkylbenzene industry chain, produce surfactants, liquid detergents and other downstream products, and realize the development of the whole industry chain of alkylbenzene.
"The project not only adopts the most advanced technology in China, its biggest highlight is energy saving and emission reduction." Dai Jin introduced that energy-saving, water-saving and power-saving measures are taken in the design of each specialty, including heat integration between devices, optimization of steam pipeline network configuration, step-by-step utilization of steam, full consideration of condensate recycling as well as reuse of process wastewater after treatment, etc., to reduce water consumption, and enhance the recovery and utilization of low-temperature waste heat for optimal energy utilization. In addition, solar hot water system and solar photovoltaic power generation system are set up on the roofs of some buildings within the project to realize energy saving and emission reduction.
Anchor the goal and work hard for a long time. For the development prospects of the project, Zhang Chunsheng, secretary of the Party Committee of Jinling Petrochemical and executive director, is full of expectations, "This is a key step for Jinling Petrochemical to promote the integration of 'oil conversion', 'oil to special' and new energy development, which will This is a key step in the promotion of 'oil conversion', 'oil to special' and the integration of new energy development, which will promote the extension of the production of enterprises from surfactants to high-end products in the washing industry, which will help the industry to strengthen and supplement the chain and extend the chain, change the mode of economic growth, and realize sustainable development. At the same time it will consolidate Nanjing's industrial position as the world's largest production base of alkylbenzene and boost the extension of Nanjing's traditional chemical industry to fine chemicals."
It is worth mentioning that, as the only professional park in Nanjing that focuses on the development of modern chemical industry, Jiangbei New Material Science and Technology Park is accelerating industrial transformation and upgrading by taking the construction of major projects as a hand. The park has set up a service task force, and a person responsible for follow-up, to open up the difficulties and blockages in the construction of the project, and to promote the Jinling Petrochemical high-end daily chemicals project to be completed and put into production early.