This provincial major project, sprinting to the top in July

Fighting for major projects!

Nanrui Jibao Intelligent Electrical Equipment

Industrial Park Phase II Project Site

It's a hot mess.

More than 600 workers stick to their posts

Sprinting for a full cap in July

Nanrui Jibao Intelligent Electrical Equipment Industrial Park Phase II project is a major project in Jiangsu Province and Nanjing City, with a total investment of 2 billion yuan and a construction area of 194,000 square meters. The project consists of five buildings, including high-rise plant, low-rise plant and shift building.Nanrui Relay Protection is the largest scientific research and industrialization base in the field of domestic electric power protection control and intelligent electric power equipment, and one of the world's top five power system relay protection equipment supply enterprises.The construction of the second phase of the project will help Nanrui JIU successfully break through a series of key technologies in power control protection and industrial control.


This project has high positioning, high management requirements and special plant items. There are large-span roof truss beams and extra-long floor surfaces, all of which pose higher requirements for construction. The enterprise will also actively promote the application of intelligent construction in construction, including assembly construction, Bim modeling system, and will add unmanned lifts and construction robots at a later stage.

During the May 1 period, the project in the grasp of workers' services to protect at the same time, hundreds of builders stick to their posts, to protect the construction, to protect the node, sprinting to the target task of the full roof in July.

The city's new electric power (smart grid) cluster has been selected as one of the first batch of national advanced manufacturing clusters, Jiangning Development Zone last year issued a smart grid industry multiplication action plan, and strive to 2025, become a core area of the world-class smart grid industry, energy science and technology self-reliant and self-reliant innovation curator and the full range of elements of the complete international ecological smart power valley. As the backbone of theThe second phase of the industrial park project is scheduled to be completed next year, and after reaching production, it is expected to realize an additional output value of 2.5 billion yuan and a tax revenue of 200 million yuan. 